The contractor is making great progress following the severe storms in May and early June that impacted the construction schedule. Site storm drain and electrical infrastructure is complete and they are almost finished installing curb, gutter and concrete flatwork. Irrigation installation, sod and planting has been underway for a few weeks. We anticipate the asphalt paving operation to commence the week August 11 and the remaining site details to be completed by the week of August 25. We look forward to opening the parking lot and access road to the public for Labor Day weekend.