Cornerstone Park Maintenance Facility
The Cornerstone Maintenance Facility project responds to identified deficiencies and growing operational demands within South Suburban Park and Recreation District’s maintenance system. A district-wide study completed by Stantec evaluated existing service centers, including the Cornerstone site, and found that as the District continues to grow and maintenance demands expand, the need for a modern, strategically located maintenance facility at Cornerstone Park has become increasingly urgent to improve operational efficiency, support staff, and ensure reliable, high-quality maintenance services for the community.
The Cornerstone Maintenance Facility project responds to identified deficiencies and growing operational demands within South Suburban Park and Recreation District’s maintenance system. A district-wide study completed by Stantec evaluated existing service centers, including the Cornerstone site, and found that as the District continues to grow and maintenance demands expand, the need for a modern, strategically located maintenance facility at Cornerstone Park has become increasingly urgent to improve operational efficiency, support staff, and ensure reliable, high-quality maintenance services for the community.
-
Proposed Cornerstone Park Conceptual Site Plan
Share Proposed Cornerstone Park Conceptual Site Plan on Facebook Share Proposed Cornerstone Park Conceptual Site Plan on X (formerly Twitter) Share Proposed Cornerstone Park Conceptual Site Plan on Linkedin Email Proposed Cornerstone Park Conceptual Site Plan link
Following the recommendations of the 2024 Maintenance Facility Evaluation, South Suburban has developed a Conceptual Site Plan Amendment for Cornerstone Park.
The proposed plan includes:
- A new maintenance and operations facility on approximately three acres on the east side of the park.
- Administrative offices, maintenance and storage areas, covered equipment storage, and secured operational areas.
- A new inclusive playground.
- A picnic shelter and restroom.
- Space reserved for a future splash pad.
- Relocation of the existing skate park within Cornerstone Park.
The proposal is intended to address long-term operational needs while continuing to provide recreational opportunities and future park improvements.
Learn more about the proposed site plan and the upcoming review and approval process on Game Plan.
Following the recommendations of the 2024 Maintenance Facility Evaluation, South Suburban has developed a Conceptual Site Plan Amendment for Cornerstone Park.
The proposed plan includes:
- A new maintenance and operations facility on approximately three acres on the east side of the park.
- Administrative offices, maintenance and storage areas, covered equipment storage, and secured operational areas.
- A new inclusive playground.
- A picnic shelter and restroom.
- Space reserved for a future splash pad.
- Relocation of the existing skate park within Cornerstone Park.
The proposal is intended to address long-term operational needs while continuing to provide recreational opportunities and future park improvements.
Learn more about the proposed site plan and the upcoming review and approval process on Game Plan.
-
Join Us at the Cornerstone Park Public Information Meeting
Share Join Us at the Cornerstone Park Public Information Meeting on Facebook Share Join Us at the Cornerstone Park Public Information Meeting on X (formerly Twitter) Share Join Us at the Cornerstone Park Public Information Meeting on Linkedin Email Join Us at the Cornerstone Park Public Information Meeting link
South Suburban Park and Recreation District invites community members to attend a public information meeting regarding the proposed Cornerstone Park Conceptual Site Plan Amendment.
Staff will share information about:
- The proposed maintenance facility
- Planned park improvements
- Potential relocation of skate facilities
- Potential relocation of the inline rink facility to another South Suburban location pending evaluation.
- The City of Englewood Planned Unit Development (PUD) Amendment process
- Opportunities for public feedback
Date: Wednesday, November 18, 2026
Time: 6:00 - 7:30 p.m.
Location: Buck Community Recreation Center
2004 W. Powers Ave., Littleton, CO 80120Community members are invited to learn more about the proposed plan, project background, and next steps before a formal PUD Amendment application is submitted to the City of Englewood.
South Suburban Park and Recreation District invites community members to attend a public information meeting regarding the proposed Cornerstone Park Conceptual Site Plan Amendment.
Staff will share information about:
- The proposed maintenance facility
- Planned park improvements
- Potential relocation of skate facilities
- Potential relocation of the inline rink facility to another South Suburban location pending evaluation.
- The City of Englewood Planned Unit Development (PUD) Amendment process
- Opportunities for public feedback
Date: Wednesday, November 18, 2026
Time: 6:00 - 7:30 p.m.
Location: Buck Community Recreation Center
2004 W. Powers Ave., Littleton, CO 80120Community members are invited to learn more about the proposed plan, project background, and next steps before a formal PUD Amendment application is submitted to the City of Englewood.
-
2024 Maintenance Facility Evaluation
Share 2024 Maintenance Facility Evaluation on Facebook Share 2024 Maintenance Facility Evaluation on X (formerly Twitter) Share 2024 Maintenance Facility Evaluation on Linkedin Email 2024 Maintenance Facility Evaluation link
In 2024, South Suburban completed a district-wide maintenance facility evaluation to assess the long-term needs of park maintenance operations. The study found that several maintenance facilities, including the existing Cornerstone Park satellite facility, are aging and no longer fully support the District's operational needs.
The evaluation recommended a modern west-side maintenance facility to improve operational efficiency, reduce travel time for maintenance crews, better distribute equipment and resources, and provide a safer and more functional work environment for staff. Cornerstone Park was identified as a potential location because of its existing maintenance presence and central location within the western service area.
The proposed facility would support the long-term maintenance of South Suburban's parks, trails, athletic fields, playgrounds, and recreation facilities while advancing goals related to efficiency, fiscal responsibility, employee safety, and stewardship of public resources.
In 2024, South Suburban completed a district-wide maintenance facility evaluation to assess the long-term needs of park maintenance operations. The study found that several maintenance facilities, including the existing Cornerstone Park satellite facility, are aging and no longer fully support the District's operational needs.
The evaluation recommended a modern west-side maintenance facility to improve operational efficiency, reduce travel time for maintenance crews, better distribute equipment and resources, and provide a safer and more functional work environment for staff. Cornerstone Park was identified as a potential location because of its existing maintenance presence and central location within the western service area.
The proposed facility would support the long-term maintenance of South Suburban's parks, trails, athletic fields, playgrounds, and recreation facilities while advancing goals related to efficiency, fiscal responsibility, employee safety, and stewardship of public resources.
26 Oct 2026
-
Email amagalhaes@ssprd.org
-
Procurement & Contracting
Cornerstone Park Maintenance Facility has finished this stageLate 2025 – March 2026
- RFQ issued and shortlist established
- RFP issued and Design-Build proposals received
- Contractor interviews conducted - February 2026
- Board approval of Design-Build team - March 2026
-
Design & Pre-Construction
Cornerstone Park Maintenance Facility is currently at this stageApril – December 2026
- Project kickoff and team onboarding
- Programming validation with maintenance staff
- Cornerstone Park Conceptual Site Plan 3rd Amendment Review
- South Suburban Board of Directors Study Session: Wednesday, November 11, 2026
- Community and stakeholder engagement
- Wednesday, November 18, 2026
- Cornerstone Park Final Site Plan 3rd Amendment Approval
- Wednesday, December 9,2026
- Design development and cost estimating
- Entitlements and permitting coordination
- Guaranteed Maximum Price (GMP) development (December 2026)
-
Final Approvals
this is an upcoming stage for Cornerstone Park Maintenance FacilityJanuary 2027
- Board approval of GMP
- Final design confirmation
- Construction mobilization planning
-
Construction
this is an upcoming stage for Cornerstone Park Maintenance FacilityMarch – December 2027
- Site preparation and initial construction activities
- Building construction and utility installation
- Ongoing coordination, inspections, and QA/QC
- Final completion and facility turnover (December 2027)