This morning, after completing a walkthrough of the renovation project, the park was officially opened.
There are a few remaining tasks for the contractor to finish, including the installation of the shelter light and delivery of a san-o-let. However, these minor items will not affect the use of the newly renovated park.
Additionally, an irrigation replacement project will begin in October and continue through Spring 2025. During this time, sections of the trail may be temporarily closed, but the playground will remain open for use. Once the project is completed in Spring 2025, we plan to celebrate with a park dedication event.
Share Construction / Park Opening Update on Facebook
Share Construction / Park Opening Update on Linkedin
Email Construction / Park Opening Update link
The majority of the park renovation project is now complete. Next week, the focus will shift to installing the asphalt parking surface and striping. Simultaneously, the contractor will begin addressing the remaining punch list items. We anticipate the parking area and the rest of the park to be open and fully operational by the end of the day on Friday, September 20.
Share New Parking Lot on Facebook
Share New Parking Lot on Linkedin
Email New Parking Lot link
The new parking lot features one accessible parking stall and nine standard parking stalls, along with enhanced drainage improvements.
Share New Tables on Facebook
Share New Tables on Linkedin
Email New Tables link
Two new standard tables and two accessible tables have been installed underneath the shelter!
Share New Benches on Facebook
Share New Benches on Linkedin
Email New Benches link
Four new benches have been installed around the playground, with companion seating provided at two of the locations
Share Shelter Installation on Facebook
Share Shelter Installation on Linkedin
Email Shelter Installation link
The new 20' x 20' shelter has been installed and the concrete flatwork is scheduled to be poured early next week.
Share Playground Poured In Place Installation - Complete on Facebook
Share Playground Poured In Place Installation - Complete on Linkedin
Email Playground Poured In Place Installation - Complete link
The playground rubber safety surfacing and engineered wood fiber chips have been installed.
Share Playground Surfacing Subgrade Prep on Facebook
Share Playground Surfacing Subgrade Prep on Linkedin
Email Playground Surfacing Subgrade Prep link
The playground surfacing subgrade is being prepped for concrete and rubber safety surfacing.
Share Drinking Fountain Install on Facebook
Share Drinking Fountain Install on Linkedin
Email Drinking Fountain Install link
The new accessible drinking fountain with a dog bowl & bottle filler has been installed!
Share Playground Equipment Install on Facebook
Share Playground Equipment Install on Linkedin
Email Playground Equipment Install link
Playground equipment was delivered to the site last week. Once all playground equipment is installed, the contractor will begin preparing the subgrade for concrete and rubber safety surfacing.