We use cookies to ensure our site functions properly and to store limited information about your usage. You may give or withdraw consent at any time. To find out more, read our privacy policy and cookie policy.
Manage Cookies
A cookie is information stored on your computer by a website you visit. Cookies often store your settings for a website, such as your preferred language or location. This allows the site to present you with information customized to fit your needs. As per the GDPR law, companies need to get your explicit approval to collect your data. Some of these cookies are ‘strictly necessary’ to provide the basic functions of the website and can not be turned off, while others if present, have the option of being turned off. Learn more about our Privacy and Cookie policies. These can be managed also from our cookie policy page.
Strictly necessary cookies(always on):
Necessary for enabling core functionality. The website cannot function properly without these cookies. This cannot be turned off. e.g. Sign in, Language
Analytics cookies:
Analytical cookies help us to analyse user behaviour, mainly to see if the users are able to find and act on things that they are looking for. They allow us to recognise and count the number of visitors and to see how visitors move around our website when they are using it. Tools used: Google Analytics
Share Little Dry Creek Park Improvements Project on FacebookShare Little Dry Creek Park Improvements Project on TwitterShare Little Dry Creek Park Improvements Project on LinkedinEmail Little Dry Creek Park Improvements Project link
Project is Complete
South Suburban is making improvements to the Little Dry Creek Park playground area! The area was last improved in 2002. Improvements will include new modern-themed playground equipment, rubberized safety surfacing within the playground footprint, a new post-tension basketball court, a larger shade pavilion that incorporates more seating, and the addition of a san-o-let and san-o-let enclosure. Concrete walkways and playground surfacing will be upgraded to provide better accessibility within the core of the park.
South Suburban is making improvements to the Little Dry Creek Park playground area! The area was last improved in 2002. Improvements will include new modern-themed playground equipment, rubberized safety surfacing within the playground footprint, a new post-tension basketball court, a larger shade pavilion that incorporates more seating, and the addition of a san-o-let and san-o-let enclosure. Concrete walkways and playground surfacing will be upgraded to provide better accessibility within the core of the park.
Share PIP - Top Layer on FacebookShare PIP - Top Layer on TwitterShare PIP - Top Layer on LinkedinEmail PIP - Top Layer link
The poured in place rubber safety surfacing was installed yesterday, as well as the san-o-let enclosure. The shelter erection process has begun and it is anticipated to be complete by the end of the week.
Share Post Tension Basketball Court - Concrete Pour on FacebookShare Post Tension Basketball Court - Concrete Pour on TwitterShare Post Tension Basketball Court - Concrete Pour on LinkedinEmail Post Tension Basketball Court - Concrete Pour link
The post tension basketball court was poured this morning.
Share PIP - Base Layer on FacebookShare PIP - Base Layer on TwitterShare PIP - Base Layer on LinkedinEmail PIP - Base Layer link
The poured in place rubber safety surfacing base layer is being installed today. The base layer is an all black layer which will then be topped with a blue, green, and black layer tomorrow.
Share Concrete - 4" Subbase on FacebookShare Concrete - 4" Subbase on TwitterShare Concrete - 4" Subbase on LinkedinEmail Concrete - 4" Subbase link
The 4" concrete subbase for the poured in place rubber safety surfacing was installed today. The base layer for the safety surfacing will be installed next Monday and the top or colorful layer will be installed on Tuesday.
Share Shelter and San-O-Let Pad Caissons on FacebookShare Shelter and San-O-Let Pad Caissons on TwitterShare Shelter and San-O-Let Pad Caissons on LinkedinEmail Shelter and San-O-Let Pad Caissons link
The shelter and san-o-let pad caissons have been drilled and the rebar cages have installed. We are anticipating these caissons to be poured by the end of the week pending inspections.
Share Post Tension Basketball Court - Formed on FacebookShare Post Tension Basketball Court - Formed on TwitterShare Post Tension Basketball Court - Formed on LinkedinEmail Post Tension Basketball Court - Formed link
The post tension basketball court has been formed and the tendons have been installed. We are anticipating concrete to be poured Monday, November 13 weather dependent.
Share Playground Curb - Concrete Install on FacebookShare Playground Curb - Concrete Install on TwitterShare Playground Curb - Concrete Install on LinkedinEmail Playground Curb - Concrete Install link
The playground curb was poured today. The contract has also begun fine grading the playground footprint in preparation of the concrete subbase. The concrete subbase pour has been pushed back a couple days due to the fact that we would like to rotate the dinosaur 180 degrees so it is facing the shelter vs. the soccer fields.
Share Playground Curb on FacebookShare Playground Curb on TwitterShare Playground Curb on LinkedinEmail Playground Curb link
The playground curb is being formed and will be poured tomorrow Friday, November 3. Once the playground curb is poured, fine grading within the playground footprint will take place in preparation for concrete subbase and poured-in-place rubber safety surfacing.