Littleton Golf & Tennis Parking Lot Improvements
Design work is underway for improvements to the parking lot. The project includes raising the grade of the parking lot to pipe the irrigation flow from the Bowles Grove Pond to the driving range lake, separating trail access to the Mary Carter Greenway from vehicle/cart traffic, and converting the pond on the corner of Federal Blvd. and Bowles Ave. to a storm water basin. Other improvements include landscape islands in the parking lot, enhanced landscaping along Federal Blvd. and Bowles Ave., and the addition of a small shade pavilion near the Mary Carter Greenway Trail connection.
Design work is underway for improvements to the parking lot. The project includes raising the grade of the parking lot to pipe the irrigation flow from the Bowles Grove Pond to the driving range lake, separating trail access to the Mary Carter Greenway from vehicle/cart traffic, and converting the pond on the corner of Federal Blvd. and Bowles Ave. to a storm water basin. Other improvements include landscape islands in the parking lot, enhanced landscaping along Federal Blvd. and Bowles Ave., and the addition of a small shade pavilion near the Mary Carter Greenway Trail connection.
-
Construction Update
Share Construction Update on Facebook Share Construction Update on X (formerly Twitter) Share Construction Update on Linkedin Email Construction Update linkStaff will recommend an award of contract to the Board of Directors at their October 14 meeting.
Staff will recommend an award of contract to the Board of Directors at their October 14 meeting.
-
Construction Update
Share Construction Update on Facebook Share Construction Update on X (formerly Twitter) Share Construction Update on Linkedin Email Construction Update linkStaff anticipate going out to bid in June for this project. Construction is still anticipated to occur October 2026 - May 2027.
Staff anticipate going out to bid in June for this project. Construction is still anticipated to occur October 2026 - May 2027.
-
Construction Update
Share Construction Update on Facebook Share Construction Update on X (formerly Twitter) Share Construction Update on Linkedin Email Construction Update linkStaff rejected all bids and will resubmit the 404 permit under the new 2026 Nationwide Permit system. Staff plans to rebid the project once the new 404 permit is issued, with construction anticipated to begin at the end of October and conclude in May 2027 with the project being completed in one phase.
Staff rejected all bids and will resubmit the 404 permit under the new 2026 Nationwide Permit system. Staff plans to rebid the project once the new 404 permit is issued, with construction anticipated to begin at the end of October and conclude in May 2027 with the project being completed in one phase.
-
Permitting Approved
Share Permitting Approved on Facebook Share Permitting Approved on X (formerly Twitter) Share Permitting Approved on Linkedin Email Permitting Approved linkThe City of Littleton and the U.S. Army Corps of Engineers have completed their review of the construction drawings, and the project is now being prepared for bidding and construction. The project is anticipated to be completed in two phases, with Phase 1 beginning in the spring and Phase 2 in fall 2026.
The City of Littleton and the U.S. Army Corps of Engineers have completed their review of the construction drawings, and the project is now being prepared for bidding and construction. The project is anticipated to be completed in two phases, with Phase 1 beginning in the spring and Phase 2 in fall 2026.
-
Construction Documents - Third Submittal
Share Construction Documents - Third Submittal on Facebook Share Construction Documents - Third Submittal on X (formerly Twitter) Share Construction Documents - Third Submittal on Linkedin Email Construction Documents - Third Submittal linkStaff received comments from the City of Littleton on the third submittal of construction documents. Comments will be addressed prior to the contractor submitting for construction permits. Additionally, comments from U.S. Army Corps of Engineers were addressed and the 408 permit was re-submitted; however, the Corps has notified us of a funding shortage in the Section 408 Program for fiscal year 2025, that has impacted their ability to progress toward a decision on our Section 408 request. It is unclear at this time when will the permit will be reviewed.
Staff received comments from the City of Littleton on the third submittal of construction documents. Comments will be addressed prior to the contractor submitting for construction permits. Additionally, comments from U.S. Army Corps of Engineers were addressed and the 408 permit was re-submitted; however, the Corps has notified us of a funding shortage in the Section 408 Program for fiscal year 2025, that has impacted their ability to progress toward a decision on our Section 408 request. It is unclear at this time when will the permit will be reviewed.
-
Construction Documents - Second Submittal
Share Construction Documents - Second Submittal on Facebook Share Construction Documents - Second Submittal on X (formerly Twitter) Share Construction Documents - Second Submittal on Linkedin Email Construction Documents - Second Submittal linkStaff received comments from the City of Littleton on the second submittal of construction documents. Staff anticipates submitting a third construction document package to the City by mid-March. Additionally, comments from U.S. Army Corps of Engineers were addressed and the 408 permit was re-submitted.
Staff received comments from the City of Littleton on the second submittal of construction documents. Staff anticipates submitting a third construction document package to the City by mid-March. Additionally, comments from U.S. Army Corps of Engineers were addressed and the 408 permit was re-submitted.
-
Design Is Underway
Share Design Is Underway on Facebook Share Design Is Underway on X (formerly Twitter) Share Design Is Underway on Linkedin Email Design Is Underway linkStaff is working with the design team and City of Littleton on improvements.
Staff is working with the design team and City of Littleton on improvements.
9 October 2026
-
Design and Construction Supervisor
Email JOdrzywolski@ssprd.org
-
Planning & Design
Littleton Golf & Tennis Parking Lot Improvements is currently at this stageSpring 2024 - Spring 2026
-
Construction
this is an upcoming stage for Littleton Golf & Tennis Parking Lot ImprovementsOctober 2026 - May 2027