Construction Documents - Second Submittal

Staff received comments from the City of Littleton on the second submittal of construction documents. Staff anticipates submitting a third construction document package to the City by mid-March. Additionally, comments from U.S. Army Corps of Engineers were addressed and the 408 permit was re-submitted.

Share Construction Documents - Second Submittal on Facebook Share Construction Documents - Second Submittal on Twitter Share Construction Documents - Second Submittal on Linkedin Email Construction Documents - Second Submittal link