Construction Update
Installation of water, storm, and sewer pipes within South Suburban property is nearly complete. Xcel is relocating gas and electrical lines to a new easement away from future courts and vertical structures. Douglas County issued permits for the restroom buildings, courts, fencing, and lighting. The contractor is now installing electrical conduit as well as concrete curb and gutter.
The project is complete, and the facility is now open.