Share Project Complete! on Facebook
Share Project Complete! on Linkedin
Email Project Complete! link
The playground surfacing project is now substantially complete! A few minor punch list items remain and will be addressed after the upcoming holiday.

Share Poured-in-Place Rubber (PIP) Safety Surfacing Installation on Facebook
Share Poured-in-Place Rubber (PIP) Safety Surfacing Installation on Linkedin
Email Poured-in-Place Rubber (PIP) Safety Surfacing Installation link
The PIP surfacing was installed last week; however, while the material was curing over the weekend a fence panel was knocked down damaging a small section. The contractor will be onsite next week to make the surface repair. As of now, we are anticipating the project being complete by the end of the day Thursday, July 03.

Share Concrete Subbase Installation on Facebook
Share Concrete Subbase Installation on Linkedin
Email Concrete Subbase Installation link
The concrete subbase for the new poured-in-place (PIP) rubber safety surfacing has been installed. The PIP material has been ordered and is scheduled for delivery and installation within the next 1–2 weeks.
The construction fence will remain in place around the playground equipment until the project is complete; however, the concrete path separating the 2–5 and 5–12 playground areas is open for use.
Please proceed with caution while construction is ongoing.


Share Mobilization and Demolition on Facebook
Share Mobilization and Demolition on Linkedin
Email Mobilization and Demolition link
The contractor has mobilized and begun demolition. Demolition is anticipated to be complete this afternoon with concrete subbase installation occurring Thursday (06/12) and Friday (06/13).

Share Preconstruction Meeting on Facebook
Share Preconstruction Meeting on Linkedin
Email Preconstruction Meeting link
A preconstruction meeting was held on site to discuss the project schedule and potential concerns. It is anticipated the project will start the week of June 09 and be completed the week of July 07.
Share Bidding Process on Facebook
Share Bidding Process on Linkedin
Email Bidding Process link
The project has completed the bidding process and we anticipate having a contractor on board to begin this project in June.
Share Planning Process Underway on Facebook
Share Planning Process Underway on Linkedin
Email Planning Process Underway link
The planning and design process to replace the rubber safety tiles with traditional poured-in-place (PIP) rubber surfacing is now underway.