Province Center Park Playground Surfacing

Share Province Center Park Playground Surfacing on Facebook Share Province Center Park Playground Surfacing on Twitter Share Province Center Park Playground Surfacing on Linkedin Email Province Center Park Playground Surfacing link
Aerial photo of playground at Province Center

The rubber tile playground safety surfacing is approaching the end of its useful life. South Suburban has initiated a renovation effort to replace the tiles with traditional poured-in-place (PIP) rubber safety surfacing. The removal of the existing tiles and installation of the new PIP surfacing are anticipated to begin in mid-June and be completed by mid-July of this year.

The rubber tile playground safety surfacing is approaching the end of its useful life. South Suburban has initiated a renovation effort to replace the tiles with traditional poured-in-place (PIP) rubber safety surfacing. The removal of the existing tiles and installation of the new PIP surfacing are anticipated to begin in mid-June and be completed by mid-July of this year.

  • Poured-in-Place Rubber (PIP) Safety Surfacing Installation

    Share Poured-in-Place Rubber (PIP) Safety Surfacing Installation on Facebook Share Poured-in-Place Rubber (PIP) Safety Surfacing Installation on Twitter Share Poured-in-Place Rubber (PIP) Safety Surfacing Installation on Linkedin Email Poured-in-Place Rubber (PIP) Safety Surfacing Installation link

    The PIP surfacing was installed last week; however, while the material was curing over the weekend a fence panel was knocked down damaging a small section. The contractor will be onsite next week to make the surface repair. As of now, we are anticipating the project being complete by the end of the day Thursday, July 03.



  • Concrete Subbase Installation

    Share Concrete Subbase Installation on Facebook Share Concrete Subbase Installation on Twitter Share Concrete Subbase Installation on Linkedin Email Concrete Subbase Installation link

    The concrete subbase for the new poured-in-place (PIP) rubber safety surfacing has been installed. The PIP material has been ordered and is scheduled for delivery and installation within the next 1–2 weeks.

    The construction fence will remain in place around the playground equipment until the project is complete; however, the concrete path separating the 2–5 and 5–12 playground areas is open for use.

    Please proceed with caution while construction is ongoing.


  • Mobilization and Demolition

    Share Mobilization and Demolition on Facebook Share Mobilization and Demolition on Twitter Share Mobilization and Demolition on Linkedin Email Mobilization and Demolition link

    The contractor has mobilized and begun demolition. Demolition is anticipated to be complete this afternoon with concrete subbase installation occurring Thursday (06/12) and Friday (06/13).

  • Preconstruction Meeting

    Share Preconstruction Meeting on Facebook Share Preconstruction Meeting on Twitter Share Preconstruction Meeting on Linkedin Email Preconstruction Meeting link

    A preconstruction meeting was held on site to discuss the project schedule and potential concerns. It is anticipated the project will start the week of June 09 and be completed the week of July 07.

  • Bidding Process

    Share Bidding Process on Facebook Share Bidding Process on Twitter Share Bidding Process on Linkedin Email Bidding Process link

    The project has completed the bidding process and we anticipate having a contractor on board to begin this project in June.

  • Planning Process Underway

    Share Planning Process Underway on Facebook Share Planning Process Underway on Twitter Share Planning Process Underway on Linkedin Email Planning Process Underway link

    The planning and design process to replace the rubber safety tiles with traditional poured-in-place (PIP) rubber surfacing is now underway.

Page last updated: 25 Jun 2025, 01:24 PM