Puma Park Improvements Project
Designs for a new playground at Puma Park are underway! Proposed improvements include upgraded playground equipment and rubberized safety surfacing to increase accessibility around the playground. A new shade pavilion and san-o-let enclosure will replace the existing structures which are at the end of their useful life. New park benches as well as standard and ADA accessible picnic tables will provide comfortable places for people to rest while visiting the playground. The planning and design of this playground are funded by South Suburban and the City of Centennial.
Designs for a new playground at Puma Park are underway! Proposed improvements include upgraded playground equipment and rubberized safety surfacing to increase accessibility around the playground. A new shade pavilion and san-o-let enclosure will replace the existing structures which are at the end of their useful life. New park benches as well as standard and ADA accessible picnic tables will provide comfortable places for people to rest while visiting the playground. The planning and design of this playground are funded by South Suburban and the City of Centennial.
-
Planning Update
Share Planning Update on Facebook Share Planning Update on Twitter Share Planning Update on Linkedin Email Planning Update linkThe City of Centennial approved the Site Improvement Plan on June 13. The design consultant is proceeding with 100 percent construction drawings for the playground improvements and developing plans for an ADA accessible walk to the ballfields. Construction of the ADA accessible walk will take place following completion of the playground improvements this fall.
-
Planning Update
Share Planning Update on Facebook Share Planning Update on Twitter Share Planning Update on Linkedin Email Planning Update linkStaff submitted an updated site plan and 75 percent construction drawings for review by the City of Centennial the latter half of May. The design consultant will prepare 100 percent construction drawings upon receipt of plan review comments from the City.
-
Planning Update
Share Planning Update on Facebook Share Planning Update on Twitter Share Planning Update on Linkedin Email Planning Update linkStaff reviewed first submittal comments with the design consultant in early April. Staff met with the design team and Southeast Metro Stormwater Authority in the later part of April to discuss impacts of proposed improvements on stormwater conveyance across the site. The design consultant is making the necessary changes and will submit updated construction drawings to the City for a second round of review at the end of May.
-
Plan Submittal
Share Plan Submittal on Facebook Share Plan Submittal on Twitter Share Plan Submittal on Linkedin Email Plan Submittal linkStaff submitted the site plan for the first round of review by City of Centennial in early February. Upon completion, the design consultant will address any comments from the City and submit further developed construction drawings for review.
-
Plan Pre-submittal
Share Plan Pre-submittal on Facebook Share Plan Pre-submittal on Twitter Share Plan Pre-submittal on Linkedin Email Plan Pre-submittal linkStaff presented preliminary plans for Puma Park improvements to City of Centennial. The design consultant is developing plans and incorporating changes based on comments from the City.
-
Design Contract
Share Design Contract on Facebook Share Design Contract on Twitter Share Design Contract on Linkedin Email Design Contract linkSouth Suburban contracted with a design consultant in May. Staff and designer had a kick-off meeting and visited the site to discuss design opportunities and constraints. The design consultant initiated construction drawings and anticipates completing a final plan set in November 2024.
-
Public Art Display
Share Public Art Display on Facebook Share Public Art Display on Twitter Share Public Art Display on Linkedin Email Public Art Display linkThe South Suburban Public Art Committee selected Puma Park as the location for a new public art installation. The artist is refining design details while SSPRD staff are coordinating installation of the art piece along with other upcoming park improvements.
-
Playground Equipment
Share Playground Equipment on Facebook Share Playground Equipment on Twitter Share Playground Equipment on Linkedin Email Playground Equipment linkBased on input from the open house and public input survey that took place in July 2023, the playground equipment shown below is proposed.
-
Site Plan
Share Site Plan on Facebook Share Site Plan on Twitter Share Site Plan on Linkedin Email Site Plan link
Last Updated
13 June, 2025
Who's Listening
-
Park Planner II
Funding Partners
Timeline
-
Public Input Survey
Puma Park Improvements Project has finished this stageResidents were invited to respond to a public input survey from July 7-24, 2023.
-
Open House
Puma Park Improvements Project has finished this stageResidents are invited to attend an open house on July 18 from 4-6 pm to learn more about plans for the park. This event will take place under the shade pavilion near the Puma Park playground.
-
Planning & Design Development
Puma Park Improvements Project has finished this stageJuly 2023 - July 2024
-
Construction Drawings & City Review
Puma Park Improvements Project is currently at this stageAugust 2024 - June 2025
-
Bidding Process & Pre-construction Coordination
this is an upcoming stage for Puma Park Improvements ProjectJuly - Aug 2025
-
Construction
this is an upcoming stage for Puma Park Improvements ProjectAugust - December 2025
-
Park Dedication
this is an upcoming stage for Puma Park Improvements ProjectSpring 2026