TrailMark Park Playground Improvements
Designs for a new playground at TrailMark Park are complete! Proposed improvements include upgraded playground equipment and rubberized safety surfacing to increase accessibility around the playground. A new shade pavilion will replace the existing structure which is at the end of its useful life. New park benches, as well as standard, and ADA accessible picnic tables will provide comfortable places for people to rest while visiting the playground.
Please Note: This project is not related to the TrailMark Community Amenities project. Visit the TrailMark Community Amenities page to learn more.
Designs for a new playground at TrailMark Park are complete! Proposed improvements include upgraded playground equipment and rubberized safety surfacing to increase accessibility around the playground. A new shade pavilion will replace the existing structure which is at the end of its useful life. New park benches, as well as standard, and ADA accessible picnic tables will provide comfortable places for people to rest while visiting the playground.
Please Note: This project is not related to the TrailMark Community Amenities project. Visit the TrailMark Community Amenities page to learn more.
-
Right of Way Ramp - Concrete Form/Pour
Share Right of Way Ramp - Concrete Form/Pour on Facebook Share Right of Way Ramp - Concrete Form/Pour on Twitter Share Right of Way Ramp - Concrete Form/Pour on Linkedin Email Right of Way Ramp - Concrete Form/Pour linkThe contractor will begin installing the concrete right of way ramp at the corner of W TrailMark Pkwy and S Flower Way starting Thursday, June 27 through Friday, June 28. While construction is happening in this area, the northbound lane along S Flower Way will be closed. Traffic control measures and flaggers will be in place to direct traffic around the construction. Please click on the exhibit below for more information.
-
2 Rail Fence Installation
Share 2 Rail Fence Installation on Facebook Share 2 Rail Fence Installation on Twitter Share 2 Rail Fence Installation on Linkedin Email 2 Rail Fence Installation linkThe contractor will begin working on the installation of a 2 rail fence that will parallel the Hildebranch Ranch Route trail adjacent to S Flower Way and S Field Way. We highly encourage trail users to utilize the sidewalk verse the crusher fines trail while this working is ongoing. The first phase of the trail work is scheduled to begin Friday, June 21 and continue through Wednesday, June 26. Please click on the exhibit below for more information.
-
Concrete Flatwork from the Intersection - Poured
Share Concrete Flatwork from the Intersection - Poured on Facebook Share Concrete Flatwork from the Intersection - Poured on Twitter Share Concrete Flatwork from the Intersection - Poured on Linkedin Email Concrete Flatwork from the Intersection - Poured linkThe concrete flatwork from the W TrailMark Parkway and S Flower Way intersection has been poured. The contractor will begin grading back the slopes, back filling, making necessary irrigation adjustments and installing sod.
-
Curb, Gutter, & Heavy Duty Concrete - Poured
Share Curb, Gutter, & Heavy Duty Concrete - Poured on Facebook Share Curb, Gutter, & Heavy Duty Concrete - Poured on Twitter Share Curb, Gutter, & Heavy Duty Concrete - Poured on Linkedin Email Curb, Gutter, & Heavy Duty Concrete - Poured link -
Curb, Gutter, & Heavy Duty Concrete - Formed
Share Curb, Gutter, & Heavy Duty Concrete - Formed on Facebook Share Curb, Gutter, & Heavy Duty Concrete - Formed on Twitter Share Curb, Gutter, & Heavy Duty Concrete - Formed on Linkedin Email Curb, Gutter, & Heavy Duty Concrete - Formed linkThe curb, gutter, and heavy duty concrete for the accessible parking spaces has been formed.
-
Concrete Flatwork Adjacent to PG Curb - Poured
Share Concrete Flatwork Adjacent to PG Curb - Poured on Facebook Share Concrete Flatwork Adjacent to PG Curb - Poured on Twitter Share Concrete Flatwork Adjacent to PG Curb - Poured on Linkedin Email Concrete Flatwork Adjacent to PG Curb - Poured link -
Trail Closures 06/05
Share Trail Closures 06/05 on Facebook Share Trail Closures 06/05 on Twitter Share Trail Closures 06/05 on Linkedin Email Trail Closures 06/05 linkA portion of the crusher fines trail south of the playground will be closed tomorrow from 8am - 2pm to install sections of playground drainage system. Please use caution if you are using the trail in that area.
-
Playground Drainage
Share Playground Drainage on Facebook Share Playground Drainage on Twitter Share Playground Drainage on Linkedin Email Playground Drainage linkThe playground drainage system is being installed and backfilled along the southern edge of the playground footprint.
-
Playground Curb - Poured
Share Playground Curb - Poured on Facebook Share Playground Curb - Poured on Twitter Share Playground Curb - Poured on Linkedin Email Playground Curb - Poured linkThe playground curbs and east bench pads have been poured.
-
Playground Curb - Formed
Share Playground Curb - Formed on Facebook Share Playground Curb - Formed on Twitter Share Playground Curb - Formed on Linkedin Email Playground Curb - Formed linkThe new playground curb and bench pads have been staked and formed. These will be poured early this week. Additionally, the playground footprint grade is being raised to new elevations to allow for the installation of the concrete subbase and poured in place rubber safety surfacing at the northern portion of the footprint adjacent to the concrete flatwork.
Last Updated
27 June 2024
Who's Listening
-
Park Planner II
Email WBarringer@ssprd.org
Timeline
-
Public Input
TrailMark Park Playground Improvements has finished this stage- Public input was collected in-person at the Littleton Meet Greet & Eat on July 13, 2022
- An online survey was open from May 9-31, 2022
-
Planning & Design
TrailMark Park Playground Improvements has finished this stageJune - August 2023
-
Bid Process
TrailMark Park Playground Improvements has finished this stageJanuary - March 2024
-
Construction
TrailMark Park Playground Improvements is currently at this stageApril - Summer 2024