TrailMark Park Playground Improvements

Share TrailMark Park Playground Improvements on Facebook Share TrailMark Park Playground Improvements on Twitter Share TrailMark Park Playground Improvements on Linkedin Email TrailMark Park Playground Improvements link
Photo of the current playground at TrailMark Park

Designs for a new playground at TrailMark Park are complete! Proposed improvements include upgraded playground equipment and rubberized safety surfacing to increase accessibility around the playground. A new shade pavilion will replace the existing structure which is at the end of its useful life. New park benches, as well as standard, and ADA accessible picnic tables will provide comfortable places for people to rest while visiting the playground.


Please Note: This project is not related to the TrailMark Community Amenities project. Visit the TrailMark Community Amenities page to learn more.

Designs for a new playground at TrailMark Park are complete! Proposed improvements include upgraded playground equipment and rubberized safety surfacing to increase accessibility around the playground. A new shade pavilion will replace the existing structure which is at the end of its useful life. New park benches, as well as standard, and ADA accessible picnic tables will provide comfortable places for people to rest while visiting the playground.


Please Note: This project is not related to the TrailMark Community Amenities project. Visit the TrailMark Community Amenities page to learn more.

  • Playground Equipment & Shelter Delay

    Share Playground Equipment & Shelter Delay on Facebook Share Playground Equipment & Shelter Delay on Twitter Share Playground Equipment & Shelter Delay on Linkedin Email Playground Equipment & Shelter Delay link

    Due to manufacturing delays, the delivery dates for the playground equipment and shelter have been postponed. We now anticipate the arrival of these materials during the week of August 5th, with installation to occur immediately upon delivery. In the meantime, minimal work will be conducted as the remaining tasks are contingent upon the installation of the playground. Items remaining until the project is complete:

    - Installation of the playground equipment

    - Installation of the 4" concrete subbase

    - Installation of the rubber safety surfacing

    - Installation of the engineered wood fiber

    - Installation of the new 20' x 20' shelter

    - Installation of shelter electrical (this item will be delayed due to an unanticipated Xcel transformer needing to be installed in the park, but will not impact opening the park)

    - Installation of site furnishings (ADA tables, tables, benches)

    - Regrading and installing new asphalt in the parking lot

    - Installing new parking lot striping

    It is anticipated that construction will be complete mid-late September.

  • 2 Rail Fence - Cedar Post Install

    Share 2 Rail Fence - Cedar Post Install on Facebook Share 2 Rail Fence - Cedar Post Install on Twitter Share 2 Rail Fence - Cedar Post Install on Linkedin Email 2 Rail Fence - Cedar Post Install link

    Majority of the post have been set for the 2 rail cedar fence paralleling S Field Way. Please continue to use caution while utilizing the trail in this area. The fence work is anticipated to be complete the week of July 22.

  • Right of Way Ramp - Poured

    Share Right of Way Ramp - Poured on Facebook Share Right of Way Ramp - Poured on Twitter Share Right of Way Ramp - Poured on Linkedin Email Right of Way Ramp - Poured link

    A new accessible 8-foot wide concrete trail, featuring truncated domes, to enhance accessibility into the park.

  • Right of Way Ramp - Concrete Form/Pour

    Share Right of Way Ramp - Concrete Form/Pour on Facebook Share Right of Way Ramp - Concrete Form/Pour on Twitter Share Right of Way Ramp - Concrete Form/Pour on Linkedin Email Right of Way Ramp - Concrete Form/Pour link

    The contractor will begin installing the concrete right of way ramp at the corner of W TrailMark Pkwy and S Flower Way starting Thursday, June 27 through Friday, June 28. While construction is happening in this area, the northbound lane along S Flower Way will be closed. Traffic control measures and flaggers will be in place to direct traffic around the construction. Please click on the exhibit below for more information.

  • 2 Rail Fence Installation

    Share 2 Rail Fence Installation on Facebook Share 2 Rail Fence Installation on Twitter Share 2 Rail Fence Installation on Linkedin Email 2 Rail Fence Installation link

    The contractor will begin working on the installation of a 2 rail fence that will parallel the Hildebranch Ranch Route trail adjacent to S Flower Way and S Field Way. We highly encourage trail users to utilize the sidewalk verse the crusher fines trail while work is ongoing in this area. The first phase of the trail work is scheduled to begin Friday, June 21 and continue through Wednesday, June 26 with the second phase starting Friday, July 05 through the week of July 22. Please click on the exhibit below for more information.

  • Concrete Flatwork from the Intersection - Poured

    Share Concrete Flatwork from the Intersection - Poured on Facebook Share Concrete Flatwork from the Intersection - Poured on Twitter Share Concrete Flatwork from the Intersection - Poured on Linkedin Email Concrete Flatwork from the Intersection - Poured link

    The concrete flatwork from the W TrailMark Parkway and S Flower Way intersection has been poured. The contractor will begin grading back the slopes, back filling, making necessary irrigation adjustments and installing sod.

  • Curb, Gutter, & Heavy Duty Concrete - Poured

    Share Curb, Gutter, & Heavy Duty Concrete - Poured on Facebook Share Curb, Gutter, & Heavy Duty Concrete - Poured on Twitter Share Curb, Gutter, & Heavy Duty Concrete - Poured on Linkedin Email Curb, Gutter, & Heavy Duty Concrete - Poured link

  • Curb, Gutter, & Heavy Duty Concrete - Formed

    Share Curb, Gutter, & Heavy Duty Concrete - Formed on Facebook Share Curb, Gutter, & Heavy Duty Concrete - Formed on Twitter Share Curb, Gutter, & Heavy Duty Concrete - Formed on Linkedin Email Curb, Gutter, & Heavy Duty Concrete - Formed link

    The curb, gutter, and heavy duty concrete for the accessible parking spaces has been formed.

  • Concrete Flatwork Adjacent to PG Curb - Poured

    Share Concrete Flatwork Adjacent to PG Curb - Poured on Facebook Share Concrete Flatwork Adjacent to PG Curb - Poured on Twitter Share Concrete Flatwork Adjacent to PG Curb - Poured on Linkedin Email Concrete Flatwork Adjacent to PG Curb - Poured link

  • Trail Closures 06/05

    Share Trail Closures 06/05 on Facebook Share Trail Closures 06/05 on Twitter Share Trail Closures 06/05 on Linkedin Email Trail Closures 06/05 link

    A portion of the crusher fines trail south of the playground will be closed tomorrow from 8am - 2pm to install sections of playground drainage system. Please use caution if you are using the trail in that area.


Page last updated: 20 Sep 2024, 01:01 PM