Abbott Park Celebration
Thursday, June 27, 4-6 pm
Join us to celebrate the renovations and upgrades at Abbott Park, 7898 S. High St., on Thursday, June 27, from 4-6 pm. The improvements include a new playground, basketball court, new benches, upgraded ADA parking spaces, and new concrete walks. Enjoy a fun scavenger hunt, treats and prizes!

Share Drinking Fountain Repair - Complete on Facebook
Share Drinking Fountain Repair - Complete on Linkedin
Email Drinking Fountain Repair - Complete link
The drinking fountain repair is complete.
Share Drinking Fountain Repair on Facebook
Share Drinking Fountain Repair on Linkedin
Email Drinking Fountain Repair link
While charging the drinking fountain, a component broke. We will be out to repair it as soon as the part is received.
Share Sod Installation - Complete on Facebook
Share Sod Installation - Complete on Linkedin
Email Sod Installation - Complete link
Sod installation at Abbott Park has been completed. While the sod roots are becoming established, we kindly ask you to please keep off the sod. The sod establishment period lasts around typically lasts two weeks, where it will be watered extensively. After the establishment period is over, the sod will return to a normal watering program.


Share Sod Installation on Facebook
Share Sod Installation on Linkedin
Email Sod Installation link
The park irrigation system will be turned on this month allowing for the installation of new sod adjacent to the playground area. This work is scheduled to take place this month.
Share Shelter Lights - Installed on Facebook
Share Shelter Lights - Installed on Linkedin
Email Shelter Lights - Installed link
Two new solar powered shelter lights have been installed. These lights are different than the previous ones and do not require an electrical cabinet. Parks is going to monitor the functionality of the lights for a few weeks prior to removing the cabinet pad and conduit at the shelter column base. 

Share Park Open! on Facebook
Share Park Open! on Linkedin
Email Park Open! link
While there are a handful of items that need to be addressed we are excited to announce that the park is now open. Due to the time the project was completed sod will be installed in spring of 2024. Following the installation of sod, a Park Dedication event will be held by South Suburban.


Share Shelter Lights on Facebook
Share Shelter Lights on Linkedin
Email Shelter Lights link
We are currently waiting on new light fixtures for the shelter and removing the graffiti off the existing electrical cabinet.


Share Basketball Court - Goal Post, Backboard, and Hoop Install on Facebook
Share Basketball Court - Goal Post, Backboard, and Hoop Install on Linkedin
Email Basketball Court - Goal Post, Backboard, and Hoop Install link
Share New Asphalt at S High St Parking Lot on Facebook
Share New Asphalt at S High St Parking Lot on Linkedin
Email New Asphalt at S High St Parking Lot link
New asphalt has been installed at the S High St. parking lot.