Fairways at Lone Tree Park Improvements

Share Fairways at Lone Tree Park Improvements on Facebook Share Fairways at Lone Tree Park Improvements on Twitter Share Fairways at Lone Tree Park Improvements on Linkedin Email Fairways at Lone Tree Park Improvements link
Photo of Fairways at Lone Tree Park

Planning and design for the renovation of the Fairways at Lone Tree Park are underway. In response to public input, the small shade pavilion near the existing parking area will be replaced by a post-tension basketball half-court. Modern playground equipment and rubberized safety surfacing will increase accessibility to and around play equipment. Additional landscape features will protect vegetation and minimize erosion. A new shade pavilion, picnic tables, and benches will replace amenities at the end of their useful life to ensure comfort for park visitors. To optimize motor vehicle access to the park, the parking lot entryway will be realigned, parking spaces will be reconfigured, and the parking lot will be resurfaced.

Planning and design for the renovation of the Fairways at Lone Tree Park are underway. In response to public input, the small shade pavilion near the existing parking area will be replaced by a post-tension basketball half-court. Modern playground equipment and rubberized safety surfacing will increase accessibility to and around play equipment. Additional landscape features will protect vegetation and minimize erosion. A new shade pavilion, picnic tables, and benches will replace amenities at the end of their useful life to ensure comfort for park visitors. To optimize motor vehicle access to the park, the parking lot entryway will be realigned, parking spaces will be reconfigured, and the parking lot will be resurfaced.

  • Construction Update

    Share Construction Update on Facebook Share Construction Update on Twitter Share Construction Update on Linkedin Email Construction Update link

    Playground installation is nearly complete. The contractor will pave the parking lot and install shelter caissons when weather permits. The shelter and san-o-let enclosure will be installed upon arrival in the spring.

  • Construction Update

    Share Construction Update on Facebook Share Construction Update on Twitter Share Construction Update on Linkedin Email Construction Update link

    Construction is progressing as planned. Contractors installed boulder walls, landscaping, post tension court, and much of the ADA accessible walkway. Playground equipment delivery and installation is scheduled for November.


  • Park Construction

    Share Park Construction on Facebook Share Park Construction on Twitter Share Park Construction on Linkedin Email Park Construction link

    Construction in the park will begin September 10, 2024 and is anticipated to be complete at the end April, 2025. The fields will remain open, but the playgrounds, shade pavilions, and parking lots will be inaccessible during this time. Please use caution during park construction and check back here for the most up to date project information.

  • Planning Update

    Share Planning Update on Facebook Share Planning Update on Twitter Share Planning Update on Linkedin Email Planning Update link

    The Site Improvement Plan was approved by the City of Lone Tree and South Suburban received final construction drawings on May 21, 2024. The project has gone out to bid and a construction contract will be proposed during the July 10 meeting with the Board of Directors.

  • Site Plan

    Share Site Plan on Facebook Share Site Plan on Twitter Share Site Plan on Linkedin Email Site Plan link

  • Playground Designs Available to View

    Share Playground Designs Available to View on Facebook Share Playground Designs Available to View on Twitter Share Playground Designs Available to View on Linkedin Email Playground Designs Available to View link

    Based on responses to an online survey from Oct. 17-31, 2022, the playground equipment pictured below is planned.


Page last updated: 13 Dec 2024, 11:56 AM